110/15 kV Towarowa Substation

Construction of 110/15 kV Towarowa substation and reconstruction of 110/15 kV Poznań Główna substation to improve the power supply to the city of Poznań is an investment undertaking of Enea Operator Sp. z o.o. and it was implemented with co-financing from EU funds (Infrastructure and Environment Fund and European Regional Development Fund).

Line

Construction of the 110/15 kV Towarowa substation | Poland

Victor Energy was able to provide the client with a project management group that was experienced in every aspect of engineering, delivery, installation and commissioning of their project which helped translate this project into a reality for the city of Poznań.

The project required extensive communication with regulatory authorities in the city of Poznań due to the proximity of the electrical infrastructure to existing facilities and required a lengthy and precise permitting process. The requirement to rebuild an advanced substation in the tight confines of traditional and historically significant buildings presented a challenge to the city of Poznań to complete.

The project required extensive communication with regulatory authorities in the city of Poznań due to the proximity of the electrical infrastructure to existing facilities and required a lengthy and precise permitting process. The requirement to rebuild an advanced substation in the tight confines of traditional and historically significant buildings presented a challenge to the city of Poznań to complete.

Line

City Center Distribution Point

The 110/15kV Towarowa substation construction was required to expand the grid in the city of Poznań, and act as a distribution point for energy for the city center. Our qualified staff, experience in obtaining formal and legal permits related to investment, and experience in SF6 GIS systems and their implementation in restrictive settings enables Victor Energy to deliver the work.

Line

The scope of work included:

The project required extensive communication with regulatory authorities in the city of Poznań due to the proximity of the electrical infrastructure to existing facilities and required a lengthy and precise permitting process. The requirement to rebuild an advanced substation in the tight confines of traditional and historically significant buildings presented a challenge to the city of Poznań to complete.

Line

The scope of work included:

The project required extensive communication with regulatory authorities in the city of Poznań due to the proximity of the electrical infrastructure to existing facilities and required a lengthy and precise permitting process. The requirement to rebuild an advanced substation in the tight confines of traditional and historically significant buildings presented a challenge to the city of Poznań to complete.

Line

Additional details of the work:

Line

Works on the project started in January 2020
and finished by February 2023.